Terrace House Renovation in the Klang Valley: Cost, Timeline and Planning Guide

The double-storey terrace is the most common home in the Klang Valley, and most were built 20 to 40 years ago. A good renovation can make an old terrace feel brighter, cooler and bigger. This guide explains what it costs and how to plan it.

By the KAIU design & build team · Reviewed by Dr. Foo Yan Wen, Director, KAIU Concept & Construction · Updated November 2026

Quick answer

  • Partial renovation (kitchen, bathrooms, flooring): about RM50,000 to RM150,000.
  • Full interior design & build of a landed home: about RM120,000 to RM350,000.
  • Typical timeline: 2 to 4 weeks design, then about 3 to 6 months on site.
  • Fix the roof, wiring and plumbing first. Finishes come last.

What a full terrace renovation usually includes

  • Hacking walls to open the living, dining and dry kitchen
  • New wet and dry kitchen, often with a rear extension
  • Bathroom renovation with waterproofing
  • Rewiring, new lighting and air-conditioning points
  • Flooring, ceiling, painting and feature walls
  • Built-in wardrobes, TV cabinet and shoe cabinet
  • Facade, gate, porch and roof repairs
Warm dining area with feature pendant light by KAIU
KAIU design: contemporary home, Newton Road

Cost guide (Klang Valley, 2026)

Scope Guide cost
Kitchen renovation (cabinets and finishes) RM25,000 to RM70,000
Bathroom renovation (per bathroom) RM12,000 to RM30,000
Partial renovation (kitchen, bathrooms, flooring, paint) RM50,000 to RM150,000
Full interior design & build RM120,000 to RM350,000
Rear extension (if added) RM250 to RM400 per sq ft

Guide prices for the Klang Valley, 2026. Your quote depends on site condition, size and materials.

The right order of work

  1. Survey and design
    Measure the house, check roof, wiring and plumbing, and agree the layout and 3D design.
  2. Approval if needed
    Extensions and structural changes need council approval. Internal finishes usually do not.
  3. Hacking and structure
    Demolition, extension structure, new openings.
  4. Services
    Electrical, plumbing, air-con piping and waterproofing.
  5. Finishes
    Ceiling, tiles, flooring and paint.
  6. Carpentry and handover
    Cabinets installed, final cleaning, defect check and handover.
KAIU tip: If you plan to extend the kitchen in the next few years, do it together with the renovation. Doing it later means hacking new tiles and paying twice for the same work.
Living room with timber slat wall and white sofa by KAIU
KAIU design: living room, Lim residence
Want a clear, itemised quotation? Send your floor plan and a few photos to WhatsApp 011-1309 3099. We reply with next steps and arrange a free site visit anywhere in Kuala Lumpur and the Klang Valley.

Common mistakes to avoid

  • Assuming all renovation work is permit-free. Structural changes and extensions need approved plans.
  • Not checking hidden problems like roof leaks, termites and old wiring before choosing finishes.
  • Choosing tiles and cabinets before the electrical and plumbing layout is fixed.

Frequently asked questions

How much does it cost to renovate a terrace house in KL?

As a guide, a partial renovation is about RM50,000 to RM150,000 and a full interior design & build is about RM120,000 to RM350,000, depending on size and finishes.

How long does a terrace house renovation take?

About 2 to 4 weeks for design, then about 3 to 6 months on site for a full renovation.

Can I live in the house during renovation?

For a partial renovation, sometimes. For a full renovation we usually recommend moving out, because water and power will be cut at times and there is a lot of dust.

Which council do I apply to for renovation in the Klang Valley?

It depends on where the house is: for example DBKL for Kuala Lumpur, MBPJ for Petaling Jaya, MBSJ for Subang Jaya and Puchong, and MBSA for Shah Alam. Each council has its own forms and rules.

Do minor renovations need a permit?

Simple works such as painting, tiling or replacing cabinets usually do not need plan approval. Structural changes, extensions and changes to the facade do. We check this for you during the site visit.

What hidden problems are common in older terrace houses?

Roof leaks, termites, old wiring that cannot take today’s power load, and rusty pipes. It is best to find and budget for these before finishes go in.

Do I need to upgrade my electricity supply?

Older houses often need a new distribution board and, if you add many air-conditioners or an induction hob, a supply upgrade with TNB. Your electrician will advise based on your load.

Renovating a terrace house? Talk to one team for design and build.

KAIU Concept & Construction is a CIDB-licensed interior design & build company in Kuala Lumpur. One team handles design, permits, construction and our own carpentry, from concept to handover.

We serve Kuala Lumpur, Petaling Jaya, Subang Jaya, Puchong, Cheras, Shah Alam, Klang, Mont Kiara, Bangsar and the rest of the Klang Valley.

WhatsApp 011-1309 3099Book a free site visit

Share your thoughts

Free quote? Chat with us